New Village Report Rebugre 17th feb 2023

D:\LOGO\IMG-20200618-WA0010.jpgWB.jpg

COMMUNITY LED LANDSCAPE MANAGEMENT PROJECT (CLLMP)

The Government of Meghalaya with financial help from the World Bank is implementing the Meghalaya Community Led Landscape Management Project (MCLLMP). The project covers the entire state of Meghalaya and implementation of community-led plans are rolled out in a phased manner throughout the state. The Meghalaya Basin Management Agency (MBMA) will facilitate community-led planning by providing support, technical inputs and funding.

The project is intended to strengthen community-led natural resources management in selected landscapes within the 7 districts of the state. This would be achieved through a variety of planning, capacity building, and on-the-ground interventions to promote the conservation, sustainable use of natural resources, social inclusion and community mobilization; building traditional knowledge and learning, mapping of natural resources management; strengthening the community institutions and creating linkage with financial institutions and community organizations.

The project interventions will include preparation of community led natural resource management plans. The CLLMP has the following three components:

  1. Strengthening Knowledge and Capacity of Communities for Natural Resources Management

  2. Community-Led Landscape Planning and Implementation

  3. Project Management and Governance

The project objective is “to manage and conserve the natural resources, especially forests, soil and water sources, in a manner that supports the financial and physical well-being of communities in the State”

INTRODUCTION

Rebugre village is situated under the Dadenggre C&RD block of West Garo Hills district of Meghalaya. The village is about 5 km from the Dadenggre Block and 61km from the district Headquarter, Tura. The village is under the traditional land owner of A’king Nokma. The total population and the demographic of both male and female of the village is about 482 with 86number of household. The village Latitude is 25.75360°North and Longitude 090.19724°East.

The total geographical area of the village is around 607.69 Ha with 6.0769sq.Km.

Rebugre_Boundary Map.jpg

SOCIAL PROFILE

The Village is about 5Km away from Dadenggre Block and 61 km away from district headquarter Tura. The public transport facilities to and from village is in Pick up and private vehicle. In respect to the Social Mobilization, it wasn’t that difficult to handle the community of this village as they are active and hardworking. Despite of very less facilities available, the community are very keen towards achieving the aims and objectives of CLLMP.

Fuel /LPG /biomass/gas most of the households are using Woods and very less access to LPG. The community has few facilities such as education, safe drinking water supply, road and access to medical facilities. The village is under Head of village (Nokma). About 100 households still uses woods for cooking whereas about 2 households use LPG.

Rebugre village has total no of 102 households with the total population of 476. Out of which are 242 males and 234 are females.

The following is the demographic break up information acquired by the CLLMP team of WGH district.

C:\Users\User\Downloads\1. Communities Inhabiting.png

C:\Users\Acer\Desktop\WGH Team Activities\2020\40 CNRMP Villages\Simchi LULC_WGH\Rebugre_lulc.jpg

C:\Users\User\Downloads\2. Occupation.png

Agriculture is the main source of the village. Rebugre village are still into farming which includes agriculture and multi cropping. Areca nut is always one of the most grown cash crops followed by cashew nut, banana, pineapple, black pepper etc.

There are 102 HH Farmer.

C:\Users\User\Downloads\4. Land Use Pattern.png

C:\Users\User\Downloads\3. Key constraints in the Village.png

C:\Users\User\Downloads\5. Environmental Challenge.png

ACTIVITIES

GROUND TRUTHING AND SENSITIZATION PROGRAMME

F:\Village Report Ajita\Rebugre\Sensitizaton programme at Rebugre Village on the 2nd July 2020\WhatsApp Image 2020-07-03 at 9.17.31 PM.jpeg

DPMU team of West Garo Hills visited Rebugre village for Sensitization cum Ground Truthing on 3rd July 2020.

CASE FINDINGS AND LIST OF NATURAL RESOURCES.

  1. The village has102 HH with 476 total populations.

  2. The village water sources are springs and streams. It has 5 streams and 8 springs.

  3. The village has indigenous tree species such as :-Tebrong, Tegatchu, Sakap, Bolchu, Aminsep, Bolcchim, Bolbret, Prap, Soksimareng, Gambare, Chigambal, Champal, Sirore, Gimbil, Achri, Bandikgiri, Bolbok, Rengok, Gasampe, ambare, Tekra, Tepatang, siso

  4. The village Forest has medicinal shrubs/trees such as Tebrong, Tegatchu, Letchu, Gasampe, Komperam, Komila, Amabare, tekra, tepatang, soksimareng, tekreng, Darichek, angkil

  5. Commercially valued Trees/ Shrubs/Plants in forests available in the village forest are Gambare, sampal, bolbret, bolchim, agajari, siso

  6. The village has Fodder/Valuable grass available such as Ampang, Mesenachil, Samskal, Samchachi

  7. Water scarcity during winter season.

  8. Land Degradation

PRA EXERCISE AND CNRM PLAN PREPARATION F:\Village Report Ajita\Rebugre\PRA and CNRMP at Rebugre Village on the 10th July 2020\PRA and CNRM Plan conducted at Rebugre village under Dadenggre Block, WGH district on the 10th July 2020. On the sam by AM-EM, PA-GIS and FE.jpeg

The District team of West Garo Hills conducted PRA and CNRM plan on 10th July 2020 at Rebugre Village Dadenggre Block, WGH.

The exercises were conducted by the district team Environment, GIS and Field Engineer. The Team informed the community that PRA exercise is to understand and locate the natural resources of the village and plan the activities according to their need. The community had an exercise to plan and draw resource and social map on the same day.

In the exercise of CNRM plan preparation, the community were asked to prioritized the plan /activities and submit the plan to DPMU for 5 years. The exercises were done in the presence of village headmen, VNRMCs and Village facilitators.

  1. Signing of Documents:

As an acceptance and agreement to the project, every member of the village households had to sign green charter on 10th July 2020 and submitted the Village agreement and Expression of Interest to DPMU.

  1. Formation of the VNRMC

On 10thJuly 2020, after the ground survey and sensitization programme, the village signed the EOI, VGA and Green charter as a sign of accepting the project. Whereas in regards, to the selection of Village Natural Resource Management Committee(VNRMC) members the Village Executive Committee (VEC) along with entire community carried out the process of selecting 15 chosen members such as 9 Executive members, 3 Purchase committee and 3 Village Community Facilitator .

  1. Listed below are the members of the VNRMC:

Sl No Name in Full Gender M/F Age (in Yrs) Education Designation Occupation Community Contact No and email address
1  Jetden Marak M 40  primary  Chariman  farmer  Garo 9366399300
2 Satilla marak F 28 X Secretary  farmer Garo __
3 Denjilla Marak f  member  farmer  Garo
4 Solmith Marak M 31 X  member  farmer Garo 6009163366
5  Diwen Sangma M 29  primary  member  farmer  Garo 6009087982
6 Jemusa sangma F  member  farmer Garo
7 Jenesh marak F  member  farmer Garo
8 Sengsram Sangma M  member  farmer Garo
Natson sangma M    member  farmer Garo  9366871752
9

Village Community Facilitators (VCF)

Sl No Name in Full Gender M/F Age
(Yrs)
Education Area of specialisation/ focus (forests, water, soil, accounts, environmental and social safeguards, knowledge management, GIS) Trained under CLLMP (Yes/ No?) if Yes, date training was received Contact No and email address
1 Shri Sengran Sangma M NRM/GIS 6009357367
2 Shri Tenggat M Sangma M 28 Class 10 SM/KM Yes 9863094265
3 Shri Hillon Ch Marak M 33 Class 9 M&E Yes 9366152695

Plan Estimate:

The DPMU team of WGH made an inspection to the proposed intervention sites soon after the CNRM plan preparation gets over.

PROJECT IMPLEMENTATION

Sl No

Implemented Activities Name of Site Work Status
1. RCC Check Dam Chinakaltok Chiring Completed
2. Community Nursery Rongganggap Gittim Completed
3. Plantation LP School Compound Completed
4. PCC Water Conservation Dam (2-Units) Rongmeram Completed
5. Spring Chamber Chinakaltok Chimik Completed
6. Spring Chamber Ronggrim Chimik Completed
7. RCC Check Dam Rongganggap Chiring Completed
8. Dug out Pond Banding Chiring Completed
9. Composting pit Rongganggap Gittim, Near Nursery Completed
10. Water Conservation Dam (Additional) Songgitcham Chimik Completed
11. Permanent Community Nursery (Balance fund) Chakrang Chisam

4. Fund Status

1 Type Of Intervention Site Name GPS Co-ordinates Amount Work Status
RCC Check Dam ChinakaltokChiring Elevation 140m N 25.75653 E 090.19569 Rs.4,57,500 Completed

D:\Village Report\Village Report 2021\Rebugre 11th Oct 2021\WhatsApp Image 2021-10-12 at 9.34.38 AM (1).jpeg

2 Type Of Intervention Site Name GPS Co-ordinates Amount Work Status
Community Nursery Rongganggap Gittim Elevation 178m N25.747904 E090.190321 Rs.1,00,000 Completed

D:\Village Report\Village Report 2021\Rebugre 11th Oct 2021\WhatsApp Image 2021-10-12 at 8.41.18 AM.jpeg

3 Type Of Intervention Site Name GPS Co-ordinates Amount Work Status
Plantation LP School Compound Elevation: 219m N25.75385° E090.19763° Rs.46,000 Completed

C:\Users\vivi\Documents\1645081812924.jpg

Before After

4 Type Of Intervention Site Name GPS Co-ordinates Amount Work Status
PCC Water Conservation Dam (2-Units) Rongmeram Elevation 192m N 25.74868° E 090.19168° Rs.4,89,000 Completed

5 Type Of Intervention Site Name GPS Co-ordinates Amount Work Status
Spring Chamber Chinakaltok Chimik

Elevation 156m N 25.75616

E 090.19630

Rs. 2,20,000 Completed

E:\Field visit photos\Rebugre\Spring chamber, Chinakaltok chimik, Rebugre, Dadenggre block, WGH (4).jpeg

E:\Field visit photos\Rebugre\Spring chamber, Ronggrim chimik, Rebugre, Dadenggre block, WGH (6).jpeg

6 Type Of Intervention Site Name GPS Co-ordinates Amount Work Status
Spring Chamber Ronggrim Chimik

Elevation 219m N 25.754268

E 090.19004

Rs. 2,35,500 Completed
7 Type Of Intervention Site Name GPS Co-ordinates Amount Work Status
RCC Check Dam Rongganggap Chiring

Elevation 203m N 25.74768

E 090.18960

Rs.4,20,000 Completed

Before After

8 Type Of Intervention Site Name GPS Co-ordinates Amount Work Status
Dug out Pond Banding Chiring Elevation 182m N 25.756519° E 090.202256° Rs. 1,15,000 Completed

Before After

9 Type Of Intervention Site Name GPS Co-ordinates Amount Work Status
Composting pit Rongganggap Gittim, Near Nursery Elevation 180m N 25.747746° E 090.190330° Rs. 72,000 Completed

Before After

10 Type Of Intervention Site Name GPS Co-ordinates Amount Work Status
Water Conservation Dam (Additional) Songgitcham Chimik Elevation 189m N 25.75604 E 90.19674 Rs.500,000 Completed

Before After

11 Type Of Intervention Site Name GPS Co-ordinates Amount Work Status
Permanent Community Nursery (Balance fund) Chakrang Chisam Elevation 169m N25.74456 E90.1935 Rs.3,00,000