Umsawmat village report

UMSAWMAT VILLAGE

VNRMC DISTRICT PROJECT MANAGEMENT UNIT (DPMU)

EAST KHASI HILLS DISTRICT

The Government of Meghalaya has launched its flagship program, the Integrated Basin Development Project (IBDLP) in 2012. IBLP is a citizen-centric and demand-driven program that focuses on the development of community participation and capacity building as the pathway to sustainable eco-systems development.

Nestled under IBDPL, the Community Led Landscape Management Programme of the Government of Meghalaya looks at natural resources management through a community-led landscape approach. The Community-Led Landscape Management Project (CLLMP), which receives support from the World Bank, is a part of the CLLM-Programme.

The project interventions will include preparation of community led natural resource management plans.

The CLLMP has the following three components:

Objective:

“To manage and conserve the natural resources, especially forests, soil and water sources, in a manner that supports the financial and physical well-being of communities in the state”

Scope:

Benefits:

Implementation Agency:

The Project will be executed by the MBMA in collaboration with other partners particularly, SIRD (for training and capacity building), Department of Soil and Water Conservation, Water Resource Department, Forest Department, specifically with respect to technical inputs, safeguards management and Community NRM plan preparation.

Project Period:

2018-2023 (5 years)

About Umsawmat Village

UmasawmatVillage falls under Mawphlang C&RD Block of East Khasi Hills in the state of Meghalaya. The village lies at a distance of 16 kilometers from block headquarters Sohiong and 35kilometers from district and state capital Shillong. It falls under HimaLynniongwith a total geographical area of 1408.05 Ha and a total population of 569 from 114 households.

Village demography

Age group (in years) Male Female Total
0-4 37 33 70
5-14 105 65 170
15-30 98 88 186
31-60 50 53 103
Above 60 18 22 40
Total 308 261 569

Important dates and events

Village Functionary Members

Sl. No. Name Gender Age (in years) Educational Qualification Designation Contact Numbers
1. RoningJala M 60 III Headman 9863180424
2. LambhaKharshandi M 30 B.TECH Secretary 7005382804
3. DilestarKharshandi M 45 BA Assistant Secretary 9366426566

Village Natural Resource Management CommitteeMembers

Sl. No. Name Gender Age (in years) Educational Qualification Designation Contact Numbers
1. WanlangKharshandi M 33 IX President 6009758063
2. WanrishishaMarbaniang F 28 BA Secretary 6009192702
3. MirbilaKharshandi M 58 IX Treasurer 6009219659
4. JimestarMyrthong M 36 V Member 6009192702
5. MrislindaKharsahnoh F 40 III Member 8731051360
6. DramedaMarbaniang F 45 VII Member 8132009046
7. BanyllaMarbaniang F 26 V Member 8729970255
8. SimoraKharshandi F 30 VI Member 8131830943
9. PisarMyrthong M 38 II Member 9612111684

Village Community Facilitators Members

Sl. No. Name Gender Age (in years) Educational Qualification Environment/ Social/ M&E Contact Numbers
1. PynsuklinMyrthong F 33 X Environment 6009219659
2. AnishaMarbaniang F 29 X Social 6009478941
3. Apshonlang Rani M 30 X M&E 6009709308

Village Maps

Umsawmat_boundary.jpg

Illustration: Boundary Map of Umsawmat Village

Umsawmat.jpg

Illustration: Land Use Land Cover Map of Umsawmat Village

Village Infrastructure

The social mapping done at Umsawmat village, shows the following findings. There are two schools in the village, a church and a restricted grove.

Illustration: Social Mapping ofUmsawmat

List of Interventions

The following interventions have been implemented in Umsawmat Villageas a result of the residents' collective decision to help alleviate their problems and aid in the development of the village as well as the preservation of the village's natural resources.

Name of Interventions Name of Site Start Date Completion Date Amount from CLLMP(₹)

Convergence

(₹)

Total

(₹)

RCC Check Dam KshaidSynkra 28-Jan-20 26-Feb-20 2,50,546 - 2,50,546
Bio Fencing KyndongSohmian 27-May-20 13-Jul-20 3,47,488 - 3,47,488
Afforestation Kyndongsohmian 20-Jul-20 07-Aug-20 3,03,970 - 3,03,970
Afforestation Lumdewip Started Completed - - -
Community Nursery KyndongSohmian 14-Jul-21 08-Oct-21 1,07,005 - 1,07,005
Organic Composting Mawkhan 10-Dec-21 04-Jan-22 6,985 - 6,985
Organic Composting Tihkhyndew 08-Dec-21 03-Jan-22 6,985 - 6,985
Organic Composting Lummawkam 08-Dec-21 03-Jan-22 6,985 - 6,985
Organic Composting Lailad 8-Dec-21 03-Jan-22 6,985 - 6,985
Organic Composting Disong 10-Dec-21 04-Jan-22 6,985 - 6,985
Organic Composting Umdiang 8-Dec-21 3-Jan-22 6,985 - 6,985
Organic Composting Sohjhursaw 15-Jan-22 15-Feb-22 6,985 - 6,985
Organic Composting Shohmaw 10-Dec-21 4-Jan-22 6,985 - 6,985
Organic Composting Shyiap 15-Jan-22 15-Feb-22 6,985 - 6,985
Organic Composting Traimaw 10-Dec-21 04-Jan-22 6,985 - 6,985
Organic Composting Perrit 08-Dec-21 03-Jan-22 6,985 - 6,985
Organic Composting Shilingumbah 8-Dec-21 3-Jan-22 6,985 - 6,985
Fireline Control Dewip 18-Jan-21 15-Feb-22 54,020 - 54,020
Bench Terracing Semmali 4-Feb-22 07-May-22 45,487 - 45,487
Bench Terracing MawryngkangKlew 17-Feb-22 9-Apr-22 45,487 - 45,487
Bench Terracing Umngi 8-Mar-22 26-Apr-22 45,487 - 45,487
Bench Terracing Mawbuhshun 28-Feb-22 21-Mar-22 45,487 - 45,487
Bench Terracing Sitmaw 23-Feb-22 15-Mar-22 45,487 - 45,487
Spring Chamber ShiliangUmbah 5-Jul-22 8-Aug-22 47,242 - 47,242
Spring Chamber Mawkhan 18-Mar-22 30-Apr-22 52,835 - 52,835
Spring Chamber Photsiej 3-Feb-22 27-Apr-22 55,835 - 55,835
Protection Wall PdengMawkroh 21-Mar-22 26-Apr-22 1,54,599 - 1,54,599
Protection Wall Tihlyntiang 3-May-22 4-July-22 1,39,943 - 1,39,943
Irrigation CC Canal Umsurong 15-Mar-22 10-May-22 1,53,154 - 1,53,154
Irrigation CC Canal Umtin 19-Mar-22 10-May-22 71,743 - 71,743
RCC Check Dam Umtin 15-Mar-22 09-May-22 1,04,674 - 1,04,674
Protection Wall MadanDewip 9-Jan-23 20-Feb-23 1,95,328 - 1,95,328
Protection Wall Tihjaut 29-Nov-22 21-Dec-22 76,768 - 76,768
Bench Terracing Laitmawsing 8-Aug-22 25-Aug-22 45,487 - 45,487
Bench Terracing Mawpait 22-Aug-22 7-Sept-22 45,487 - 45,487
Bench Terracing Wahdewsaw 17-Aug-22 30-Aug-22 45,487 - 45,487
Bench Terracing Badenkyndong 11-Aug-22 01-Sept-22 45,487 - 45,487
Bench Terracing Phodjajew 26-Aug-22 30-Sept-22 45,487 - 45,487
Afforestation KyndongSnuin Yet to start  15,000 - 15,000
Fire Line Control Phodlakait 18-Oct-22 7-Nov-22 59,700 - 59,700
Conservation of Pitcher Plant Phodlakait 21-Oct-22 Ongoing 2,50,710 - 2,50,710
Name of Intervention Site Name Start Date Completion Date Total Amount
RCC Check Dam KshaidSynkra 28-Jan-20 26-Feb-20 ₹ 2,50,546

Illustration: RCC Check Dam at KshaidSyngkra

Name of Intervention Site Name Start Date Completion Date Total Amount
Bio Fencing KyndongSohmian 27-May-20 13-Jul-20 ₹ 3,47,488

Illustration: Bio Fencing at KyndongSohmian

Name of Intervention Site Name Start Date Completion Date Total Amount
Afforestation Kyndongsohmian 20-Jul-20 07-Aug-20 ₹ 3,03,970

Illustration: Afforestation at Kyndongsohmian

Name of Intervention Site Name Start Date Completion Date Total Amount
Community Nursery KyndongSohmian 14-Jul-21 08-Oct-21 ₹ 1,07,005

Illustration: Community Nursery at Kyndongsohmian

Name of Intervention Site Name Start Date Completion Date Total Amount
Organic Composting Mawkhan 10-Dec-21 04-Jan-22 ₹ 6,985

Illustration: Organic Composting at Mawkhan

Name of Intervention Site Name Start Date Completion Date Total Amount
Organic Composting Tihkhyndew 08-Dec-21 03-Jan-22 ₹ 6,985

Illustration: Organic Composting at Tihkhyndew

Name of Intervention Site Name Start Date Completion Date Total Amount
Organic Composting Lummawkam 8-Dec-21 03-Jan-22 ₹ 6,985

Illustration: Organic Composting at Lummawkan

Name of Intervention Site Name Start Date Completion Date Total Amount
Organic Composting Lailad 8-Dec-21 03-Jan-22 ₹ 6,985

Illustration: Organic Composting at Lailad

Name of Intervention Site Name Start Date Completion Date Total Amount
Organic Composting Umdiang 8-Dec-21 3-Jan-22 ₹ 6,985

Illustration: Organic Composting at Umdiang

Name of Intervention Site Name Start Date Completion Date Total Amount
Organic Composting Sohjhursaw 15-Jan-22 15-Feb-22 ₹ 6,985

Illustration: Organic Composting at Sohjhursaw

Name of Intervention Site Name Start Date Completion Date Total Amount
Organic Composting Shohmaw 10-Dec-21 4-Jan-22 ₹ 6,985

Illustration: Organic Composting at Shohmaw

Name of Intervention Site Name Start Date Completion Date Total Amount
Organic Composting Shyiap 15-Jan-22 15-Feb-22 ₹ 6,985

Illustration: Organic Composting at Shyiap

Name of Intervention Site Name Start Date Completion Date Total Amount
Organic Composting Perrit 08-Dec-21 03-Jan-22 ₹ 6,985

Illustration: Organic Composting at Perrit

Name of Intervention Site Name Start Date Completion Date Total Amount
Organic Composting Shilingumbah 8-Dec-21 3-Jan-22 ₹ 6,985

Illustration: Organic Composting at ShiliangUmbah

Name of Intervention Site Name Start Date Completion Date Total Amount
Fireline Control Dewip 18-Jan-21 15-Feb-22 ₹ 54,020

Illustration: Fire line Control at Dewip

Name of Intervention Site Name Start Date Completion Date Total Amount
Bench Terracing Semmali 4-Feb-22 07-May-22 ₹ 45,487

Illustration: Bench Terracing at Semmali

Name of Intervention Site Name Start Date Completion Date Total Amount
Bench Terracing Sitmaw 23-Feb-22 15-Mar-22 ₹ 45,487

Illustration: Bench Terracing at Sitmaw

Name of Intervention Site Name Start Date Completion Date Total Amount
Spring Chamber ShiliangUmbah 5-Jul-22 8-Aug-22 ₹ 47,242

Illustration: Spring Chamber at ShiliangUmbah

Name of Intervention Site Name Start Date Completion Date Total Amount
Spring Chamber Mawkhan 18-Mar-22 30-Apr-22 ₹ 52,835

Illustration: Spring Chamber at Mawkhan

Name of Intervention Site Name Start Date Completion Date Total Amount
RCC Check Dam Umtin 15-Mar-22 09-May-22 ₹ 1,04,674

Illustration: RCC Check Dam at Umtin

Name of Intervention Site Name Start Date Completion Date Total Amount
Protection Wall PdengMawkroh 21-Mar-22 26-Apr-22 ₹ 1,54,599

Illustration: Protection Wall at Pdengmawkroh

Name of Intervention Site Name Start Date Completion Date Total Amount
Protection Wall MadanDewip 9-Jan-23 20-Feb-23 ₹ 1,95,328

Illustration: Protection Wall at MadanDewip

Name of Intervention Site Name Start Date Completion Date Total Amount
Protection Wall Tihjaut 29-Nov-22 21-Dec-22 ₹ 76,768

Illustration: Protection Wall at Tihjaut

Name of Intervention Site Name Start Date Completion Date Total Amount
Bench Terracing Laitmawsing 8-Aug-22 25-Aug-22 ₹ 45,487

Illustration: Bench Terracing at Laitmawsing

Name of Intervention Site Name Start Date Completion Date Total Amount
Bench Terracing Mawpait 22-Aug-22 07-Sept-22 ₹ 45,487

Illustration: Bench Terracing at Mawpait

Name of Intervention Site Name Start Date Completion Date Total Amount
Bench Terracing Wahdewsaw 17-Aug-22 30-Aug-22 ₹ 45,487

Illustration: Bench Terracing at Wahdewsaw

Name of Intervention Site Name Start Date Completion Date Total Amount
Bench Terracing Badenkyndong 11-Aug-22 01-Sept-22 ₹ 45,487

Illustration: Bench Terracing at Baden Kyndong

Name of Intervention Site Name Start Date Completion Date Total Amount
Conservation of Pitcher Plant Phodlakait 21-Oct-22 Ongoing ₹ 2,50,710

Illustration: Conservation Area of Pitcher Plant (Endangered Plant Species) at Phodlakait